Beaumont Hospital, Construction of Car Parks & Road Realignment

Project Status
Completed
  • client
    BAM Contractors
  • Date
    2009-09-30
  • Sector
    Civil Engineering
  • Location
    Beaumont, Dublin
Beaumont Hospital, Construction of Car Parks & Road Realignment

The project consisted of the complete construction of a 308 space Permeable Car Park in Beaumont Hospital, Dublin as well as road realignment, macadam overlay, footpaths and all other associated works.

  • Design & implement traffic management system incl facilitate existing residents
  • Excavate & dispose material off site
  • Supply, place & compact various granular material
  • Realignment of existing roadway
  • Laying of new watermain, foul, storm & public lighting ducting
  • Installation of precast kerbing
  • Installation of permeable paving
  • Placement of macadam to realigned roadway
  • Installation of un-controlled pedestrian crossings
  • Installation of all road markings
  • Construction of concrete footpaths
  • Erection of timber post & rail fencing
  • Complete landscaping of area upon completion of civil works

Related Projects

Cycle Lane Upgrades

Toucan Crossing

Belgard Walkway

St James’s Hospital

O’Connell Square

Tallaght Village

Templeogue Village Initiative

1916 Plaza

Castletymon Road Works