The works consisted of the construction of new Plaza Area to commemorate the 1916 centenary year to front of St Enda’s Park. Works included installation of all public utilities, placement of polished concrete, paving, kerbing and all other ancillary works.
- Excavate & dispose material off site
- Supply, place & compact various granular material
- Laying of various utility ducting
- Installation of new public lights
- Installation of new traffic signals
- Installation of concrete & granite kerbing
- Placement of concrete footpaths
- Laying of natural stone paving
- Placement & completion of polished concrete
- Fabrication & installation of gates
- Construction of granite clad wall
- Completion of soft landscaping
- Erection of road signage
- Installation of table top ramps and macadam overlay
- Completion of road markings